During  0 - 1
  Task 1 does initialization.
  Task 2 does initialization.
During  1 - 2
  Task 1 delayed 5.
  Task 2 delayed 5.
During  2 - 3
  Task 1 delayed 4.
  Task 2 delayed 4.
During  3 - 4
  Task 1 delayed 3.
  Task 2 delayed 3.
During  4 - 5
  Task 1 delayed 2.
  Task 2 delayed 2.
During  5 - 6
  Task 1 delayed 1.
  Task 2 delayed 1.
During  6 - 7
  Task 1 completes its request (resource[1]: requested = 1, remaining = 3)
  Task 2 completes its request (resource[1]: requested = 1, remaining = 2)
During  7 - 8
  Task 1 delayed 5.
  Task 2 delayed 5.
During  8 - 9
  Task 1 delayed 4.
  Task 2 delayed 4.
During  9 - 10
  Task 1 delayed 3.
  Task 2 delayed 3.
During  10 - 11
  Task 1 delayed 2.
  Task 2 delayed 2.
During  11 - 12
  Task 1 delayed 1.
  Task 2 delayed 1.
During  12 - 13
  Task 1 completes its release (resource[1]: released = 1, available next cycle = 3)
  Task 2 completes its release (resource[1]: released = 1, available next cycle = 4)
During  13 - 14
  Task 1 delayed 5.
  Task 2 delayed 5.
During  14 - 15
  Task 1 delayed 4.
  Task 2 delayed 4.
During  15 - 16
  Task 1 delayed 3.
  Task 2 delayed 3.
During  16 - 17
  Task 1 delayed 2.
  Task 2 delayed 2.
During  17 - 18
  Task 1 delayed 1 and terminates (at 18).
  Task 2 delayed 1 and terminates (at 18).

	Run	Wait	Wait%
Task 1	18	0	0%
Task 2	18	0	0%
Total 	36	0	0%